Which of the Project Time Management processes analyzes…

Which of the Project Time Management processes analyzes activity sequencing, durations, resource
requirements, and schedule constraints?

A.
Estimate Activity Durations

B.
ControlSchedule

C.
Sequence Activities

D.
Develop Schedule