Which of the following would you send to the executive?

You are the project manager of a project .The senior executive of your company wants monthly schedule update of your project. Which of the following would you send to the executive?

A.
Milestone chart

B.
Time scaled network diagram

C.
Arrow activity diagram

D.
PERT chart