Which of the following will provide the basis for estim… seenagape 7 years ago Which of the following will provide the basis for estimating, scheduling, executing, and monitoring andcontrolling project work? A. Activities B. Milestone list C. Work breakdown structure (WBS) D. Work packages ← Previous question Next question →