Which of the following techniques uses historical information to estimate the activity duration?

Which of the following techniques uses historical information to estimate the activity duration?

A.
Three-point-estimating

B.
Organizational process assets

C.
Analogous estimating

D.
Reserve analysis

Explanation:
Estimating techniques can be applied to resources, effort, duration, and costs. The following are different methods of estimating you can use, depending on the situation.