Which of the following statements is TRUE regarding various Activity Scheduling tools?

Which of the following statements is TRUE regarding various Activity Scheduling tools?

A.
PDM allows for conditional branching and iteration of activities.

B.
PDM uses activity-on-node (AON) diagramming method.

C.
PDM allows for conditional branching and iteration of activities.

D.
PDM uses analogous methods as an estimation technique.