Which of the following statements is TRUE regarding various Activity Scheduling tools?
A.
PDM allows for conditional branching and iteration of activities.
B.
PDM uses activity-on-node (AON) diagramming method.
C.
PDM allows for conditional branching and iteration of activities.
D.
PDM uses analogous methods as an estimation technique.