Which of the following relationship is used in the Arrow Diagramming Method [ADM] :

Which of the following relationship is used in the Arrow Diagramming Method [ADM] :

A.
Start-to-Finish

B.
Finish-to-Start

C.
Start-to-Start

D.
Finish-to-Finish