Which of the following Project Communication Management processes uses performance reports as an inp seenagape 11 years ago Which of the following Project Communication Management processes uses performance reportsas an input? A.Manage Stakeholder Expectations B.Report Performance C.Distribute Information D.Plan Communications ← Previous question Next question →