Which of the following processes includes prioritizing …

Which of the following processes includes prioritizing risks for subsequent further analysis or action by
assessing and combining their probability of occurrence and impact?

A.
Qualitative risk analysis

B.
Quantitative risk analysis

C.
Risk management planning

D.
Risk response planning