PMI Exam Questions

Which of the following processes includes prioritizing risks for subsequent further analysis or acti

Which of the following processes includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?

A.
Qualitative risk analysis

B.
Quantitative risk analysis

C.
Risk management planning

D.
Risk response planning