which of the following methods? seenagape 11 years ago As part of mid-project evaluation, your project sponsor has asked you to provide a forecast of total project cost. You should calculate the forecast using which of the following methods? A.BAC B.EAC C.ETC D.WBS ← Previous question Next question →