PMI Exam Questions

which of the following methods?

As part of a mid-project evaluation, your project sponsor has asked you to provide a
forecast of total project cost. You should calculate the forecast using which of the
following methods?

A.
BAC

B.
EAC

C.
ETC

D.
WBS