PMI Exam Questions

Which of the following is useful in Identify Risks because it permits a systemic evaluation of the w

Which of the following is useful in Identify Risks because it permits a systemic evaluation of the work?

A.
Work breakdown structure.

B.
Design specification

C.
Project slow chart

D.
Project chart