PMI Exam Questions

Which of the following is not true for a Resource Leveling:

Which of the following is not true for a Resource Leveling:

A.
Project’s Critical path may be altered

B.
Reverse resource allocation scheduling

C.
Resource based scheduling method

D.
None

Explanation:
All are true about Resource Levelling . Resource Levelling is another tool in Develop Schedule.
Resource Levelling removes the peaks and valleys of resource allocation. This technique also examines resource over allocation and critical resource allocation. This technique lets the schedule and cost slip.