PMI Exam Questions

Which of the following is NOT an input of Estimate Costs?

Which of the following is NOT an input of Estimate Costs?

A.
Earn Value Analysis

B.
Scope Baseline

C.
Risk Register

D.
Human Resource Plan

Explanation:
Earned value analysis is used during the execution of the project to determine resource consumption versus planned