PMI Exam Questions

Which of the following is an input to the Perform Qualitative Risk Analysis process?

Which of the following is an input to the Perform Qualitative Risk Analysis process?

A.
Risk register

B.
Risk data quality assessment

C.
Risk categorization

D.
Risk urgency