Which of the following is an input to a Develop Human Resource Plan?

Which of the following is an input to a Develop Human Resource Plan?

A.
Activity resource requirements

B.
Costbaseline

C.
Cost management plan

D.
Chart of accounts

Explanation:
Develop Human Resource Plan Inputs : Enterprise Environmental Factors, Organizational Process Assets and Activity resource requirements.