PMI Exam Questions

Which of the following is an estimating technique that uses the values of parameters from previous s

Which of the following is an estimating technique that uses the values of parameters from previous
similar projects for estimating the same parameter or measure for a current project?

A.
Reserve analysis

B.
Three-point estimating

C.
Parametric estimating

D.
Analogous estimating