PMI Exam Questions

Which of the following is a schematic display of the pr…

Which of the following is a schematic display of the project’s schedule activities and the logical relationships
among them?

A.
Gantt chart

B.
Project schedule network diagram

C.
Project milestone list

D.
Activity list