Which of the following correctly explains the term (Progressive elaboration) ?

Which of the following correctly explains the term (Progressive elaboration) ?

A.
Changing project specifications continuosly

B.
Elaborate tracking of the project progress

C.
Elaborate tracking of the project specifications with a change control system

D.
Project specifications becoming more explicit and detailed as the project progresses