Which of the following can generate a milestone list?

Which of the following can generate a milestone list?

A.
Define Activities

B.
Sequence Activities

C.
Estimate Activity Resources

D.
Estimate Activity Durations

Explanation:
Outputs of Define Activities: Activity list, Activity Attributes and Milestone List.