Which of the following best describes the risks that still remain after avoidance, transfer, or miti

Which of the following best describes the risks that still remain after avoidance, transfer, or mitigation responses have been implemented?

A.
Contingency risks

B.
Tertiary risks

C.
Residual risks

D.
Secondary risks