Which of the following are inputs to the Plan Procurements process?

Which of the following are inputs to the Plan Procurements process?

A.
Risk register, scope baseline, enterprise environmental factors, organizational process assets,
project schedule

B.
Risk register, scope baseline, make-or-buy decisions, organizational process assets, project
schedule

C.
Project management plan, qualified seller list, contract, enterprise environmental factors,
teaming agreements

D.
Project management plan, qualified seller list, contract, make-or-buy decisions, teaming