Which of the following are inputs into the Administer P…

Which of the following are inputs into the Administer Procurements process?

A.
Payment systems, organizational process assets update, and claims administration

B.
Inspections and audits, contract change control system, and project management plan updates

C.
Procurement documents, performance reports, and approved change requests

D.
Project documents, seller proposals, and payment systems