Which input to the Manage Stakeholder Engagement process is used to document changes that occur duri seenagape 9 years ago Which input to the Manage Stakeholder Engagement process is used to document changes thatoccur during the project? A.Issue log B.Change log C.Expert judgment D.Change requests ← Previous question Next question →