Which input to the Identify Stakeholders process provides information about internal or external par seenagape 11 years ago Which input to the Identify Stakeholders process provides information about internal or externalparties related to the project? A.Procurement documents B.Communications plan C.Project charter D.Stakeholder register ← Previous question Next question →