Which index is the calculated projection of cost performance that must be achieved on the remaining seenagape 9 years ago Which index is the calculated projection of cost performance that must be achieved on theremaining work to meet a specified management goal? A.Estimate at completion B.Cost performance C.Schedule performance D.To-complete performance ← Previous question Next question →