Which earned value management (EVM) metric is a measure…

Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources
expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?

A.
Cost variance (CV)

B.
Cost performance index (CPI)

C.
Budget at completion (BAC)

D.
Variance at completion (VAC)