PMI Exam Questions

Which cost estimate technique includes contingencies to account for cost uncertainty?

Which cost estimate technique includes contingencies to account for cost uncertainty?

A.
Vendor bid analysis

B.
Three-point estimates

C.
Parametric estimating

D.
Reserve analysis