Which activity duration estimating technique incorporates additional timing for contingency purposes seenagape 13 years ago Which activity duration estimating technique incorporates additional timing for contingency purposes? A.Analogous Estimating B.Expert Judgment C.Optimistic Estimates D.Reserve Analysis ← Previous question Next question →