When estimating initial velocity, the team should most likely:

When estimating initial velocity, the team should most likely:

A.
Discuss among the team their expectations of how many story points they can address.

B.
Discuss with the customer their expectation for the velocity of producing the product.

C.
Use a Kanban workflow to identify steps and calculate velocity.

D.
Use velocity of past iterations or make a calculated guess.