PMI Exam Questions

When a risk should be avoided?

When a risk should be avoided?

A.
The risk event has a low probability of occurrence and low impact.

B.
The risk event is unacceptable – generally one with a very high probability of occurrence and high impact.

C.
The risk can be transferred by purchasing insurance.

D.
A risk event can never be avoided.

Explanation:
Most radical avoidance strategy is shutdown the project entirely.