When a project is being performed under contract, who provides SOW ?

When a project is being performed under contract, who provides SOW ?

A.
The buyer

B.
The contractor

C.
The Project sponsor

D.
The Project manager

Explanation:
The buyer provides SOW when projects are performed under contract.