what you tell? seenagape 12 years ago If aproject with a CPI of 1.2 what you tell? A.The project is consumed fewer resources than anticipated B.The project is using fewer resources than anticipated C.The project is falling behind D.The project is running ahead of schedule ← Previous question Next question →