What type of planning is used where the work to be acco…

What type of planning is used where the work to be accomplished in the near term is planned in detail, while
work in the future is planned at a higher level?

A.
Finish-to-start planning

B.
Rolling wave planning

C.
Short term planning

D.
Dependency determination