What tool or technique of Estimate Activity Durations uses parameters such as duration, budget, size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measure for a future project?
A.
Bottom-up estimating
B.
Analogous estimating
C.
Parametric estimating
D.
Three-point estimates
Explanation:
Estimating techniques can be applied to resources, effort, duration, and costs. The following are different methods of estimating you can use, depending on the situation.