What tool or technique of Estimate Activity Durations uses parameters such as duration, budget, size

What tool or technique of Estimate Activity Durations uses parameters such as duration, budget, size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measure for a future project?

A.
Bottom-up estimating

B.
Analogous estimating

C.
Parametric estimating

D.
Three-point estimates

Explanation:
Estimating techniques can be applied to resources, effort, duration, and costs. The following are different methods of estimating you can use, depending on the situation.