PMI Exam Questions

What should you do next?

You are the project manager of a project .You have just completed the Collect Requirements and Define Scope. What should you do next?

A.
Control Scope

B.
Create WBS

C.
Value analysis

D.
Verify Scope

Explanation:
Create the WBS is the process that follows Collect Requirements and Define Scope.