PMI Exam Questions

What should be the concern?

A project has an EV of 100 workdays, an AC of 120 workdays, and a PV of 80 workdays. What
should be the concern?

A.
There is a cost underrun.

B.
There is a cost overrun.

C.
The project may not meet the deadline.

D.
The project is 20 days behind schedule.