what process would you obtain stakeholders formal acceptnce of the completed project scope? seenagape 12 years ago During what process would you obtain stakeholders formal acceptnce of the completed project scope? A.Quality Control B.Scope verification C.Scope control D.Close Project ← Previous question Next question →