what is the schedulevariance (SV) for Task 8? seenagape 7 years ago The following chart contains information about the tasks in a project. Based on the chart, what is the schedulevariance (SV) for Task 8? A. -2,000 B. -1,000 C. 1,000 D. 2,000 ← Previous question Next question →