What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) seenagape 11 years ago What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost(AC) is $150, and the earned value (EV) is $50? A.0.50 B.0.67 C.1.50 D.2.00 ← Previous question Next question →