What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost seenagape 11 years ago What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actualcost (AC) is $50, and the earned value (EV) is $25? A.$50 B.$100 C.$125 D.$175 ← Previous question Next question →