PMI Exam Questions

What is one of the objectives of Project Risk Management?

What is one of the objectives of Project Risk Management?

A.
Decrease the probability and impact of an event on project objectives.

B.
Distinguish between a project risk and a project issue so that a risk mitigation plan can be put in
place.

C.
Increase the probability and impact of positive events.

D.
Removal of project risk.