What is one of the MAJOR outputs of activity sequencing? seenagape 9 years ago What is one of the MAJOR outputs of activity sequencing? A.Responsibility assignment matrix B.Work breakdown structure update C.Project network diagram D.Mandatory dependencies list ← Previous question Next question →