What is one of the MAJOR outputs of activity sequencing? seenagape 11 years ago What is one of the MAJOR outputs of activity sequencing? A.Responsibility assignment matrix B.Work breakdown structure C.Project network diagram D.Mandatory dependencies list ← Previous question Next question →