What do project reports show during the Sprint review meeting? seenagape 11 years ago What do project reports show during the Sprint review meeting? A.Estimates compared to the baseline B.Actual results to the plan C.Return on investment (ROI) D.Earned value measurement (EVM) ← Previous question Next question →