The run chart created during the Perform Quality Control process on a project is used to show the:

The run chart created during the Perform Quality Control process on a project is used to show the:

A.
relationship between two variables

B.
data points plotted in the order in which they occur

C.
most common cause of problems in a process

D.
frequency of occurrence