The project management plan:

The project management plan:

A.
Identifies all the steps and processes that will be used after a project is initiated

B.
Steps needed to complete a project task

C.
Prepared at the begining and fixed throughout the execution of the project

D.
Includes project charter

Explanation:
The project management plan provides the overall plan for executing, monitoring, and controlling closing the project