PMI Exam Questions

The process of establishing the policies, procedures, and documentation for planning, developing, m

The process of establishing the policies, procedures, and documentation for planning, developing,

managing, executing, and controlling the project schedule is known as:

A.
Plan Schedule Management.

B.
Develop Project Charter.

C.
Develop Schedule.

D.
Plan Scope Management.