The most commonly used type of precedence relationship in the precedence diagramming method (PDM) is seenagape 12 years ago The most commonly used type of precedence relationship in the precedence diagramming method(PDM) is: A.start-to-start (SS) B.start-to-finish (SF) C.finish-to-start (FS) D.finish-to-finish (FF) ← Previous question Next question →