PMI Exam Questions

The most appropriate project life cycle model for an environment with a high level of change and ext

The most appropriate project life cycle model for an environment with a high level of change and
extensive stakeholder involvement in projects is:

A.
adaptive

B.
reflexive

C.
predictive

D.
iterative